Project Name:
Construction of 10,000 cubic meters of concrete tank at Shahid Rouhi Mallard site.
Employer:
West Water and Wastewater Company of Tehran Province
Consultant:
Ramab Asia consulting engineers
Project Location:
Martyr Rouhi Mallard
Implementation specifications of the project:
In order to increase the water supply resources of Mallard city, a contract for the construction of a concrete tank unit with a capacity of 10,000 cubic meters per hour was concluded between West Water and Sewerage Company of Tehran Province and Absar Company, and it is being carried out with a physical progress of 20%.
Project Name:
The transmission line from Jihad Square to Kohens intersection is 1955 meters long
Employer:
West Water and Wastewater Company of Tehran Province
Consultant:
Project Location:
SHAHRIAR
Implementation specifications of the project:
The project of the implementation of the sewage transmission line in the west of Shahriar city, from Jihad Square to the vicinity of the 300-bed Kohenz Hospital, with a length of 1955 meters, with a double-walled polyethylene pipe with a diameter of 1200 mm, at an average depth of 7 meters, using a tunnel method with 28 concrete manholes Prefab is produced in the workshop and installed as puzzle pieces at the place of execution. It should be noted that due to the conditions of Jihad and Basij Squares, as well as the Baba-Gorgi Beltway and the heavy traffic on this route, most of the executive operations are inevitably carried out during the night and from 1 to 5 in the morning.
Project Name:
Water supply operations, purchase of pipes and construction of reservoirs in Chitgar, Letmal, Ward Vard and Harab Dere forest parks.
Employer:
District 22 Municipality of Tehran
Consultant:
Zistab Gostar Sabz Consulting Engineers
Project Location:
District 22 of Tehran
Implementation specifications of the project:
The water supply project for the green areas of the 22nd district of Tehran includes Latmal, Eastern Chitgar, Western Chitgar, Harabeh Dareh and Wardvard parks with an area of ​​approximately 3000 hectares. The implementation area of ​​this project is approximately 160,000 meters of water distribution and transmission network for the mentioned lands. In the form of a FIM contract between Absar Company and Region 22 municipality, based on the studies conducted by consulting engineers, with the implementation of this project, the green space of Region 22 will be freed from the risk of destruction and will probably be developed, in addition to the distribution network It has been mentioned that several sources of water supply, such as the Ken River and the effluent of Tehran's 6th treatment plant, are considered as the main sources of this project.
Project Name:
Construction of the second part of the western sewage transmission line along with the pressure line of the campus
Employer:
East Water and Wastewater Company of Tehran Province
Consultant:
Jojab Nu Consulting Engineers
Project Location:
PARDIS City
Implementation specifications of the project:
1- Pipe laying operation with 800 mm diameter polyethylene sewage pipe at an average depth of 22 meters and a length of 1602 meters. 2- Pipe laying operation with a 1000 mm diameter polyethylene sewage pipe at an average depth of 25 meters and a length of 210 meters. 3- Pipe jacking operation with a 1200 mm diameter concrete pipe at a depth of 14 meters and a length of 27 meters. 4- Piping operations under pressure with a GRP pipe with a diameter of 600 mm and a length of 2212 meters. A total of 26 prefabs
Project Name:
Water transmission line from SARNEI dam to Minab treatment plant
Employer:
Iran Water and Power Resources Development Company
Consultant:
Aban Pejoh Consulting Engineers
Project Location:
BANDAR ABBAS - MINAB
Implementation specifications of the project:
Implementation of 38 km of water transmission line with 1000 mm diameter GRP pipe from Serni dam to Minab water treatment plant along with 60 concrete basins and faucets.
Project Name:
Main, sub-networks and sewer lines of NEIRIZ city
Employer:
Fars Water and Wastewater Company
Consultant:
TOUS AB Consulting Engineers
Project Location:
NEIRIZ City
Implementation specifications of the project:
The implementation of the main, semi-main and secondary lines of the sewage system by tunneling and open trenching with double-walled polyethylene pipe of Carogate with a diameter of 200 to 800 mm, a length of 52 km and a depth of 2.1 to 8 meters, and the construction of in-situ concrete, prefabricated and brick manholes. In the number of 1514 pieces, implementation of sewer branches with diameters of 110, 125 and 160 mm with push-fit UPVC pipes along with the installation of all connections and accessories including: branch kit, elbow, siphon, cover, plastic cover and cast iron housing under the valve